Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Folio Scope

Folio Endpoint Load Time

Small

10 Folios, each with 2 Projects (200 worklogs per folio)

1.76 sec

Medium

5 folios, each with 10 projects (10,000 worklogs per folio)

51.2 sec

Large

5 folios, each with 10 projects (30,000 worklogs per folio)

Timed out *

* We are currently working on improvements to address this issue

Limiting the scope is mainly achieved by choosing the correct parameters that define your project. The Tempo Budgets UI wizard is a good start but for larger Folios you should create a JQL filter BEFORE you create the Folio. This might be achieved by various JQL functions and operators available. A more complete guide with recommendations can be found here.

...