Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

In order to use manual start and finish dates within your chart, you need to enable Manual Scheduling and select the (date or date/time) fields that will store the manually set start, finish and/or milestone dates. If these fields already contain date values, Structure.Gantt will use these values to place tasks appropriately within the chart.

Manual scheduling

Once Manual Scheduling is enabled, you can adjust Start, Finish and Milestone dates directly from your Gantt chart.

...

Info

If one of the selected fields has Date type and the other one has Date/Time type, they both will be treated as Date.


Note
If you do not have access to the selected field, or the field has not been added to the appropriate screens in Jira, you may receive a /wiki/spaces/strcloud/pages/3668803778.


Read-only Values

Structure.Gantt allows you to adjust manual dates and/or work estimates simply by dragging and dropping task bars within your chart. Depending on which attribute you selected to represent these values, it may or may not be possible to update those values.

...