In an agile environment, tasks are often assigned to a specific sprint, rather than specific dates. With the Use Sprints for Manual Scheduling option enabled, tasks can be scheduled to begin and end based on sprint dates. You can also move a task to a different sprint directly from your Gantt chart.

Gantt chart scheduled by sprints

If a task has more than one sprint assigned to it, Structure.Gantt will use the most recent sprint (based on actual and/or anticipated sprint end dates) for scheduling and visualization.

Info

When tasks are scheduled by sprint, you will see the Agile

icon Image Removed

icon beside the task bar.

Image Added

Visualizing Sprints

Sprints are represented in the chart header as follows:

...

Issues that are not assigned to a sprint are placed in the Backlog panel.

Backlog panel

To assign these to a sprint, simply drag the task bar to the appropriate location on the chart or click the task bar and edit the sprint field in the Task Details Panel

...

Parallel sprints with the same start and end dates are represented on the timeline as a single bar showing the total amount of parallel sprints. When dragging a task from a board with parallel sprints, Structure.Gantt will always check which sprint you want to reassign the task to.

When the start/end dates for parallel sprints are not the same, Structure.Gantt will show them in different rows (up to a maximum of 5).