Issue dependencies may create conflicts when manual scheduling is enabled. For example, for finish-to-start dependencies, if a task is scheduled for a date earlier than its predecessor's Finish Date, Structure.Gantt will highlight this conflict.
To deal with the conflict, click the task and select one of the following actions:
...
If a task is scheduled for a fixed duration shorter than its work estimate, you will receive an error message.
When this occurs, you have a few options to resolve the conflict:
...