Items are scheduled within the Gantt chart based on the work schedule outlined in the Calendar. You can select or customize the calendar to be used from the General Configuration screen.
Structure.Gantt comes with two predefined calendars: "Standard" (40-hour work week, 9:00-17:00 every workday) and "24 Hour" (all time marked as working time). Jira administrators can edit the available calendars or create additional calendars by clicking Manage Work Calendars.
...
If you've connected Structure and Planner by Tempo, any workload schemes created in Planner will be available to use as calendars in Structure. Gantt.
Adjusting Start Times
...