By default, tasks in Structure. Gantt are automatically scheduled based on the project start date, work estimates and dependencies. If Manual Scheduling is selected in the Gantt configuration, tasks will be scheduled in the following manner, depending on the Manual Scheduling options:

...

  1. If a Start or Finish date is available, the issue will be scheduled based on these, even if it is assigned to a sprint
  2. If no Start or Finish date is available, but the issue is assigned to a sprint, the issue will be scheduled for the duration of that sprint
  3. If the issue is not assigned to a sprint, is resolved and Use Resolution Date as the Finish Date is selected, the issue will be scheduled based on its resolution date
  4. Otherwise, the issue will be automatically scheduled

...