Gantt Charts for Structure .Gantt allows you to define the precision used for scheduling and calculations. You can choose 1 minute, 1 hour or 1 day precision (1 hour is used by default).
...
For example, with the default 1 hour precision, a duration of 15 minutes will be displayed in your chart as 1 hour. A Start Date of September 12, 2022 9:45 AM would be shown as September 12, 2022 9:00 AM.
Note |
---|
Structure.Gantt rounds the value of Jira fields when doing calculations, but the field value itself is not updated. |
...