  • Time Spent + Remaining Estimate, if work has been logged for the task. 
  • Original Estimate, if no work has been logged.

Structure.Gantt will use this work estimate to determine the task's duration. If you adjust the task duration by changing the size of the task bar in the chart or editing the Work value in the Task Details Panel, these fields are updated accordingly:

...

If the Use Remaining Estimate only option is selected, Structure. Gantt will base its work estimate only on the remaining work.

...

If your organization uses another method to estimate work (such as Story Points), select the Use custom estimate option and select the appropriate Estimate Attribute where those values are stored.

Structure.Gantt will use the values in this field to determine the work required for each task. If you adjust the task duration by changing the size of the task bar in the chart or editing the Work value in the Task Details Panel, Structure. Gantt will update the value in this field.

...

If you are working on a project where teams use both time tracking and a custom estimate (or you're in the process of migrating from one to the other), you can select both options.

When both are selected:

  1. Structure.Gantt will first try to use time tracking values to determine the work estimate
  2. If there is no time tracking information available for an issue, it will use the custom estimate instead
  3. If neither are available, the Default Estimate will be used. 

...

If you adjust the task duration by changing the size of the task bar in the chart or editing the Work value in the Task Details Panel, Structure. Gantt will update the value of the preferred estimate only:

...