The Resources section of your chart is split into two panels:
...
You may only see a limited number of available resources listed here if:
- The /wiki/spaces/structure/pages/3667892017 structure has been filtered - in this case, the Resource panel will only include those resources assigned to the items left in the structure
...
Resources cannot be assigned to groups or milestones.
If an issue is treated as a group, any resources assigned to that issue will be ignored when calculating resource usage.
Backlog Panel
When using sprint-based scheduling with the Backlog panel visible, the resource requirements for backlog items will be displayed to the left of the Resource Usage panel. This allows you to quickly see how much unscheduled work has been assigned to each resource, so you can make adjustments before tasks are added to the schedule.
...
Note |
---|
In order to use Tempo data for resource availability, the Jira admin must first /wiki/spaces/structure/pages/3667959520 connect Structure and Planner. |
Overallocation
If there is more work assigned to a resource than the resource can handle, the Usage square for that block of time will be highlighted (See Team 2's usage above). This allows you to quickly identify places where you may need to revisit your timeline or work distribution.
...