The Project Start Day is used as the starting point for automatic scheduling. It appears in the Gantt chart as a vertical green line. Hover Hovering over the this green dot on top of this line to will reveal the dateday marker.
...
Setting the Project Start Day
The Project Start Day is initially selected when you create a new Gantt chart. If you change the Start Day later, automatically-scheduled tasks will be adjusted accordingly. To change the Start Day:
Open the Gantt configuration and enter a new date, OR
Click the Start Day
Marker and enter the date, or simply drag it to a new location
...
marker (if you don’t see the marker, hover over the green line to reveal it)
...
If you change the Start Day, automatically-scheduled tasks will be adjusted accordingly.
Info |
---|
In order to adjust the Start Day, users must have/wiki/spaces/structure/pages/3667913752 control access for the structure. |