Structure.Gantt highlights any scheduling conflicts with a dark red line placed on top of the task bar. To review and resolve the conflict, open the Task Details panel. The conflict will be explained at the bottom of the panel, along with resolution options.
...
Issue dependencies may create conflicts when manual scheduling is enabled. For example, for finish-to-start dependencies, if a task is scheduled for a date earlier than its predecessor's Finish Date, Structure. Gantt will highlight this conflict.
To deal with the conflict, click the task and select one of the following actions:
...
If a task is scheduled for a fixed duration shorter than its work estimate, you will receive an error message.
When this occurs, you have a few options to resolve the conflict:
...