In the General tab, you define the basic elements of your Gantt chart configuration.:

  General configurations tabImage Removed

  • Start Day -

    This is the

    The day the project

    should begin

    begins.

    All 

    When automatic scheduling

     will be based on work estimates and dependencies, with the earliest issues beginning at this date

    is applied, the earliest issues will begin on this date. Later issues will be scheduled based on a combination of this date, work estimates, and dependencies.

  • Calendar -

    Tasks

    Scheduling within the chart will be

    scheduled

    based on the selected work calendar.

  • Appearance -

    Select

    This allows you to customize the default

    look/

    color of

    your

    items in the Gantt chart and how progress is visualized.

  • Tempo mode - Select this option to use scheduling and resource data from Capacity Planner.

  • Import Settings (top of the screen) - Import the Gantt configuration from another structure. See Import Settings.

...

Appearance

The appearance section allows you to customize the way task bars appear in the Gantt chart. You can select one of the predefined color schemes, or choose a custom color scheme to match your company style:

  • Color Scheme - Select the

...

  • default color for items in your chart. You can use

...

  • one of the

...

  • provided

...

  • color schemes, or click CUSTOM to select a custom color scheme.

  • Fill

...

  • Color - Enter a custom color, either using the color picker or typing its Hex value.

  • Progress

...

  • Color - Progress can be displayed as a dark or light color over the taskbar. If you select Auto,

...

  • Gantt will pick the option that provides the most contrast to your color scheme. 

...

...

Tip

This is the default color scheme. You can also customize the color scheme for select issues by creating a Slice.

Tempo Mode

Insert excerpt
Capacity Planner (formerly Planner by Tempo)
Capacity Planner (formerly Planner by Tempo)
nameconfiguration
nopaneltrue

Scheduling and Resource Allocation with Capacity Planner

Insert excerpt
Capacity Planner (formerly Planner by Tempo)
Capacity Planner (formerly Planner by Tempo)
namescheduling
nopaneltrue

Resource Usage: Gantt vs. Capacity Planner

Insert excerpt
Capacity Planner (formerly Planner by Tempo)
Capacity Planner (formerly Planner by Tempo)
nameResource_usage
nopaneltrue

Tip

To learn more about using Capacity Planner and Gantt Charts for Structure together, see Capacity Planner Integration.