Structure.Gantt allows you to configure how progress for individual tasks and groups is calculated.

...

  1. Planned Work is based on the Work Estimate settings, in the same way we described for work estimates above
  2. Completed Work = Planned Work × Custom Progress / 100  (Custom Progress is determined by converting the value in the custom field to a range from 0 - 100)

Anchor
group
group
Progress Calculation for Groups

A group's Completed Work and Planned Work are calculated as the sums of the completed and planned work of its children: Group Progress = Σ Completed Work / Σ Planned Work.

...

Info
See above for how Completed Work and Planned Work are calculated for individual tasks.

Progress for Milestones

A milestone has no work, and its progress is undefined. A milestone does not affect the progress of its parent group.