In an agile environment, tasks are often assigned to a specific sprint, rather than specific dates. With the Use Sprints for Manual Scheduling option enabled, tasks can be scheduled to begin and end based on sprint dates. You can also move a task to a different sprint directly from your Gantt chart.

...

If a task has more than one sprint assigned to it, Structure. Gantt will use the most recent sprint (based on actual and/or anticipated sprint end dates) for scheduling and visualization.

...

Tasks that are scheduled by sprint have a Fixed Duration. They are scheduled for the entirety of the sprint, regardless of their work estimate, with the assumption that team members will work on tasks as they have availability during the sprint period, rather than in a set order or at a specific time. When calculating resource usage, Structure. Gantt spreads the work for each task evenly across the sprint.

...

Parallel sprints with the same start and end dates are represented on the timeline as a single bar showing the total amount of parallel sprints. When dragging a task from a board with parallel sprints, Structure. Gantt will always check which sprint you want to reassign the task to.

...

When the start/end dates for parallel sprints are not the same, Structure. Gantt will show them in different rows (up to a maximum of 5).

...