In the Resource Planning view, you can change the viewing options by selecting them from the Settings cogwheel:

Anchor
focus
focus
Row focus: hours and cards

...

When planning for a large team, you can use the Compress expanded rows setting to see all plans and all calendar events on one page without the need to scroll down the pages of Jira issues and events. Expanding the resource plans for individual resources can also take up a lot of space. This feature compresses and summarizes the plans into the total plans, availability, and events.

  • In the Settings cogwheel, click to check the Compress expanded rows.

    The expanded plans for resources switch to the compressed view.

  • Scroll through the expanded rows. In the Cards view, the plans under each resource are summed up, providing the total Planned Hoursper day. Click the Availability button to show the total availability per day.

...