There are different ways to plan time in the Resource Planning view, depending on the type of planning you're doing, and whether you're working in the Days or Weeks view: 

  • If Sync Plans with Jira Issues is enabled, plans are created automatically whenever a new issue is created, provided the required synced fields are filled in.

  • For medium or longer-term planning, such as the upcoming several weeks or months, you can create plans in the Weeks view. This gives you a "big picture" of how time is planned for your resources, making it easy to create period plans, or to shift planned work to other dates or even to other resources. This view is useful for resource managers and others who need to do high-level planning.

  • For short-term planning, such as for the current week or sprint, you can create plans in the Days view. This allows you to see more plan details, and easily focus on specific issues or resources. This view is useful for team leads and managers who need to manage the their team’s current workload for their team

No matter how you create a plan, the Plan Time form opens up for you to fill out. The fields that are filled out depend on how you plan time.

To access the Resource Planning view, select Planning (blue star) in the Tempo sidebar. The Resource Planning view opens with the Weeks views displayed by default. Click the Days button at the top-right Use the dropdown menu to switch views.

...

There are two types of plans you can create from Jira issues:

...

Info
  • Planning time through the Resource Planning view for other team members requires the View Plans and Manage Plans permissions for those teams.

  • Team members can plan time for themselves, whether it's work or personal time off.

  • Remember that the available working hours are defined in the Workload scheme to which the team member belongs.

...

  • If an issue is missing any of the synced fields listed above, add data to those fields - once there is data in all synced fields, a plan will automatically be created.

  • If all synced fields already have data, temporarily remove the data from a field, and then add it again.

  • Create new plans in Planner using one of the methods below.

Creating Plans with the Plan Time

...

Icon

Click the Use the Plan Time  button in the upper-right of either the Days or Weeks view.

...

icon to open the Plan Time form. This is a quick way to create a plan for any resource on any issue or project: the Plan Time form has no information filled in, so you can add whatever you need!.

...

Creating Plans in the Weeks View

...

Click on a day for a Jira issue: expand a resource in the resource list on the left (see Viewing Resources and Their Plans) to see the plans per Jira issue, then click on a day for an issue.

...

Info
  • Clicking on a day for an issue is a quick way to fill up the remaining hours in a day: the unused hours are planned for this issue and the day is fully booked. If a day is already booked, you can't add more hours this way.

  • The Start time for the plan is midnight when you create a plan this way, but you can edit the plan to change the start and end times for it.

...

Creating period plans from the Plan Time form:

Create a plan in any way you like in either the Days or Weeks view.

...

The Issues side panel on the right contains Jira issues organized by type (from predefined JQL searches). You can drag issues from the side panel to the Resource Planning view in either the Days or Weeks view, which is a quick way to create plans. See Finding Issues with the Issue Picker for more information.

To create plans by dragging issues from the side panel:

  1. Click the arrow on the right side of the window to open the Issues side panel. 

    Use arrow to open issues side panelImage Removedopen-side-panel.jpgImage Added
  2. Use the tabs at the top to find the issues you want to view in the panel, or use the Search box to find an issue.

  3. Drag the issue to the resource's timeline for whom you're planning, on the date when you want the plan to start:

  • In the Weeks view, do either to create a plan that fills up the available hours in a day:

    - Drag an issue to a day in a resource's timeline. This is useful if there are no plans yet, or there aren't plans for that issue yet.

    Planner_3_-_side_panel.gifImage RemovedPlanner_3_-_side_panel.gifImage Added

    - Expand a resource on the left to see the plans per Jira issue, then drag an issue from the panel onto the matching issue timeline.

Info

Dragging an issue to a day in the Weeks view is a quick way to fill up the remaining hours in a day: the unused hours are planned for this issue and the day is fully booked. If a day is already booked, you can't add more hours this way.

The Start time for the plan is midnight when you create a plan this way, but you can edit the plan to change the start and end times for it.

...

  • In the Days view:

    Drag the issue onto a day.

    Drag issue from issues side panel to a day in resource's timeline.Image RemovedThe Plan Time form opens for you to fill out. The number of hours in the Planned Time field is suggested according to the available hours in that day (to fully book the day) and the number of remaining estimated hours for that issue.Drag issue from side panel to a day in the resource's timeline.pngImage Added

    If a day is fully booked or an issue has no or remaining estimate, the Planned Time field is blank, so you need to enter the Plan Time form opens. Enter the number of hours you want to planplan to spend on the issue during that day in the Total plan time field.

Info

When you create plans by dragging issues from the Issues side panel, the number of remaining estimated hours (27h in the example below) and the number of hours that are planned on the issue (4h) are displayed and used to suggest hours planned.

If the remaining estimate exceeds the availability of the target resource on that day, the suggested plan is the remaining available time for that person/resource. 

Issues without remaining estimates do not have any suggested hours. 

...