Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Include Page
Tempo for Data Center Header
Tempo for Data Center Header
Page Properties

Question

How do I see the status of an issue on the Team Planning view ? 

Answer

To display the status of an issue in the Team Planning view, change the time frame to days instead of week or month and then single day plans will display the issue status. For plans of more than a day, there's no need to change the time frame as the status is displayed automatically. The display is based on the cell size, for example, a month's plan makes the cells small so the status does not appear for 1 day plan, however, with a plan of 4 days the issue status is visible with wider space.

...