The Pivot by Status report for Jira Server and Data Center displays time worked on issues in each issue status. This report spreads worked hours across all statuses for the issue, starting from the work started time. You can use only work started time by enabling Started Time In Status in the User Default Settings.
Element | What is it? | What can I do with it? |
---|---|---|
A | Previous and Next icons | Click to scroll to the previous or next week. |
B | Worked Hours icon | Select whether to display the daily, weekly, or monthly worked hours. |
C | Details icon | Select whether to show or hide every worklog. When set to Hide, entries are grouped by issue. |
D | Download icon | Click to export the report. SeeĀ Exporting and Importing Time Reports. |
E | Status Columns | Displays the time spent for each issue per status. |
F | Total row | Displays the total time spent per status, as well as the overall total. |