The Project Start Day is used as the starting point for automatic scheduling. It appears in the Gantt chart as a vertical green line. Hover over the green dot on top of this line to reveal the date.Project Start Day

Setting the Project Start Day

The Project Start Day is initially selected when you create a new Gantt chart. If you change the Start Day later, automatically-scheduled tasks will be adjusted accordingly.To change the Start Day:

  • Open the Gantt Chart Settings and enter a new date

  • Click the Start Day Marker and enter the date, or simply drag it to a new location

Changing the Project Start Day

In order to adjust the Start Day, users must have/wiki/spaces/structure/pages/3667913752.