Time Balance Report

The Time Balance Report for Jira Cloud displays all changes in the time tracking fields for issues in a certain period.

Note: There is no access to worklogs from this report page.

time_balance_callouts.png

 

Element

Description

Details

Element

Description

Details

A

Previous and Next icons

Select to scroll to the previous or next week.

B

Time display dropdown

Select to display the day, week, or month.

C

Worked Hours dropdown

Select to display the daily, weekly, or monthly worked hours.

D

Details button

Enable to display every worklog. When disabled, entries are grouped by issue.

E

Time Spent column

Displays the sum of worklogs for an issue, during the period selected. Note: There is also a Jira issue Timespent field, which is the overall value of time logged for an issue.

F

Estimate column

Displays Time Spent + Est. Time Remaining.

G

Variance column

Displays the time variance, calculated as Original Estimate - Estimate (Time Spent + Est. Time Remaining).

H

Original Estimate column

Displays the initial estimated time specified in the issue field.

I

Progress Column

Displays a progress bar to visualize the progress per issue. Calculated as Time Spent / ( Est. Time Remaining + Time Spent). Displays as 100% when Est. Time Remaining is 0.

J

Total row

Displays the total time per time column and the total progress for the displayed table.