You can quickly search for issues that you are watching and log work on an issue.
In the Log Work window, in the left column, click Watched.
Fill in the requested information.
Tips
Field | Tip |
---|---|
Issue | If the selected issue has sub-tasks, a Sub-Task field is displayed. Work is logged on the issue or on a sub-task, depending on which of the fields is active. You can recognize the active field by the gray shading in the field row. For example, in the following example, the sub-task (and not the issue) is active: |
Period | If you select the Period checkbox, an End date field for the time period is displayed. |
Worked | The number of hours that the user worked on the issue. |
Remaining estimate | The remaining estimate depends on the setting 'Remaining estimate is optional' in the Tempo global configuration:
|
Description | A description is optional if the Worklog description is optional checkbox is selected in the Tempo global configuration. |