Tempo Timesheets 8.1.0

This article is for Timesheets for Data Center. Visit Cloud

Tempo Timesheets 8.1.0

Important before you upgrade Tempo Timesheets from version 7.x.x to 8.x.x

  • The installation of Tempo Timesheets takes longer than usual because of data migration so you might want to upgrade outside of office hours.

  • Data might be lost if you downgrade to an earlier version after you upgrade Tempo Timesheets from version 7.x.x to version 8.x.x or later.

On this page

User permissions change between Tempo Timesheets 8.0 and 8.1

When you upgrade Tempo Timesheets to version 8.1.0, some Tempo permissions change to Jira permissions.

Effects of the changes

  • During the upgrade process, some Tempo permissions that your Jira users have, migrate automatically to Jira permissions.

  • Other Tempo permissions that your Jira users have might require you to prepare your old version of Tempo Timesheets so that the permissions migrate smoothly.

  • After the upgrade, Tempo Timesheets might become available for use by more Jira users in your organization.

Which permissions change?

The following table explains which permissions change:

Before the upgrade

After the upgrade

Automatic migration of users' permissions


Notes

Configuration location

Old permission

Configuration location

New permission

 > Add-ons > TEMPO Tempo Permissions

 

Tempo Administrator permission

 > System > SECURITY Global Permissions 

Tempo Administrators permission

Yes

 

Tempo Team Manager permission

Tempo Team Administrators permission

Yes

 

Tempo Account Manager permission

Tempo Account Administrators permission

Yes

 

Tempo Rate Manager permission

Tempo Rate Administrators permission

Yes

 

Tempo Time Tracking permission

Projects > View All Projects > project name > Project Administration> Permissions > Time Tracking Permissions

 

 

Work On Issues permission

Yes

Before the upgrade, only users who had Tempo Time Tracking permission could access and use Tempo Timesheets.

After the upgrade, all Jira users who have Work On Issues permission for at least one project can access and use Tempo Timesheets. The following options are displayed for all of those users:

  • Tempo option on the Jira main menu bar

  • Timesheets and Tracker options in the Tempo menu

Role to view project worklogs

View All Worklogs permission

See notes

Before the upgrade, the permission to view all worklogs for a project was granted to users who had a specified project role.

Also, users who had Approve Timesheet permission for a team could see all worklogs of team members.

After the upgrade, only users who were in the role to view project worklogs, automatically have the new View All Worklogs permission. Approve Timesheet permission is no longer sufficient to see the worklogs of team members.

 > Add-ons > TEMPO Global Configuration

User with Approve Timesheet permission can log work for team members

Log Work for Others permission

See notes

After the upgrade, users and groups who had the project role to view project worklogs, now have permission to log work for others on issues in the project.

Approve Timesheet permission no longer gives users permission to log work for other users.

Enable Time Planning

 > Add-ons > TEMPO Global Configuration

Users with Plan Time permission for a team can plan time for team members in Tempo Timesheets

No

To plan time for team members in Tempo Timesheets, the following permission is required:

Before the upgrade: Approve Timesheet permission for a team

After the upgrade: Plan Time permission for a team

 > Add-ons > TEMPO Tempo Permissions

Button for adding default members of a project role to all existing projects

In Jira, you can specify default users or groups for a project role so that, when you create a new project, those users or groups are automatically granted the role in the project.

Before the upgrade, Tempo Timesheets included a button to quickly grant those users or groups the role also in all existing projects.

After the upgrade, this button is not available.

Actions before you upgrade

Required permission

Jira Administrator permission

Procedure

Before you upgrade Tempo Timesheets to version 8.1.0, complete the following steps:

  1. If some users require permission to log work for other users, prepare your old version of Tempo Timesheets for migration of your users' permissions by completing the following steps:

  2. If you have default users or groups for a project role and you want to grant those users or groups that same role in all existing projects, do so before you upgrade Tempo Timesheets to version 8.1.0. See Adding default members to existing projects.

  3. If some of your Jira users have Work On Issues permission for a project but do not have access to Tempo Timesheets, inform them that they will have access to, and can use, Tempo Timesheets after the upgrade.

Actions after you upgrade

Required permission

Jira Administrator permission

Procedure

  1. After you upgrade Tempo Timesheets to version 8.1.0, grant View All Worklogs permission to users who have Approve Timesheet permission in any team. Grant the View All Worklogs permission to these users for the projects that are linked to their team or teams.      

  2. If some users require permission to plan time for members of a team, complete the following steps:

    1. Ensure that the following check box is selected in Tempo Global Configuration: 'Users with Plan Time permission for a team can plan time for team members in Tempo Timesheets.'

    2. Ask Team Leads or a Tempo Team Administrator to grant Plan Time permission to any users who require permission to plan time for team members.