How can I change Remaining Estimate from an Issue? (Data Center)



Question

I need to modify the Remaining Estimate in an issue, but I do not see the field. How should I do it?

Answer

If you would like to modify the Remaining Estimated you can do it through the Edit Issue Screen, given that you have the Time Tracking field configured in it.
The remaining estimate can also be adjusted when logging time on an issue.