How can I change Remaining Estimate from an Issue? (Data Center)
Question | I need to modify the Remaining Estimate in an issue, but I do not see the field. How should I do it? |
---|---|
Answer | If you would like to modify the Remaining Estimated you can do it through the Edit Issue Screen, given that you have the Time Tracking field configured in it. |
, multiple selections available,
Related content
Managing Work Estimates
Managing Work Estimates
More like this
Comparing Remaining Estimate with Planned Time
Comparing Remaining Estimate with Planned Time
More like this
Estimated cost calculations
Estimated cost calculations
Read with this
Tracking & Estimating
Tracking & Estimating
More like this
Viewing all time planned for an issue
Viewing all time planned for an issue
More like this
To create plans using the issue suggestions sidebar in Tempo for Server
To create plans using the issue suggestions sidebar in Tempo for Server
More like this