Sample Formulas - Analytics
Calculate time needed to burn down the backlog
Assuming your team can accomplish 10 story points a week, this will tell us how long (in weeks) it will take to burn down work and get to certain items further down the backlog. To adjust how many story points the team can work in a week, simply change the "velocity" value.
WITH velocity = 10:
CONCAT(SUM#preceding{story_points} / velocity, "w")
For this example to work most effectively, the structure should be sorted based on how you choose which work to complete first. See Sort Generators for more information.
Calculate days past due
This example checks for items that are overdue and returns the number of days the item is overdue.
IF dueDate < NOW():
   DAYS_BETWEEN(dueDate, NOW()) CONCAT " days late"
Compare the original estimate to work logged and the remaining estimate
IF originalEstimate:
    (timeSpent + remainingEstimate) / originalEstimate
ELSE:
    "not estimated"Â