This article is for Cloud. Visit Data Center

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

The Fixed Duration Attribute determines how fixed durations are assigned and stored. By default, Fixed Durations are stored in the Gantt Chart and can be manually set or updated using the Task Details panel or dragging its edge on the chart (when a fixed duration is set). By changing the Duration Attribute, you can automatically assign fixed durations to tasks, based on a Jira attribute or formula.


Format

If you use a custom field or formula for the Duration Attribute, you can also specify the format of values in that field. 

Fixed duration format

This tells Structure.Gantt how it should interpret the values in the field (milliseconds, minutes, hours, etc.). You can also select Text duration to use Jira duration format (1d 3h 30m).

  • No labels