List of Gantt Attributes Available in Structure
The following Gantt attributes can be used within Structure columns, formulas, transformations and Effectors. To learn more, see Gantt Attributes in Structure.
Name | Result |
---|---|
Gantt Appearance | The color of the item in the Gantt chart. Most issues will return "blue" unless they are affected by a configuration slice with a custom color scheme. |
Gantt Critical Path | Returns "Critical" if the item is part of the critical path. |
Gantt Duration | The duration of the task within the Gantt chart. |
Gantt Finish Date | The task's finish date. |
Gantt Fixed Duration | The task's fixed duration, if the task has a fixed duration. |
Gantt Leveling Delay | The delay applied to the task by resource leveling. |
Gantt Leveling Priority | The task's priority for resource leveling. When an overallocation occurs, tasks with higher priorities are placed earlier on the timeline. |
Gantt Manual Finish Date | If a task has a manual finish date, returns that date value. |
Gantt Manual Milestone Date | If a task has a manual milestone date, returns that date value. |
Gantt Manual Start Date | If a task has a manual start date, returns that date value. |
Gantt Max Units | The maximum number of resource units that can be allocated for the task at any given time (see Configuration | Resources). |
Gantt Milestone Date | If an item is visualized as a milestones within the chart, returns the milestone date. |
Gantt Progress | The calculated progress for the task. |
Gantt Resource | The resource assigned to the task. |
Gantt Scheduling Error | If a scheduling conflict exists, returns "Error" |
Gantt Scheduling Mode | Returns "Auto" if the task is automatically scheduled, "Manual" if the task is manually scheduled, "Agile" if scheduled by sprint. |
Gantt Slice | If the task's behavior or appearance is effected by a configuration slice, returns the corresponding slice's name. |
Gantt Start Date | The task's start date. |
Gantt Type | How the task is displayed in the Gantt chart: task, group or milestone. |
Gantt Work | The task's work estimate (returned as a time value), based on the Gantt configuration. If Work has been manually entered in the Task Details Panel, returns this value. |