Duplicate Plan Items & Create Templates

Teams that have repeat work will benefit from Duplicating Plan Items or converting existing Projects and Packages into Templates to move processes along more quickly. These convenience features are initiated from the right-click and 3-dot menus. Select the plan item, open the menu, and then choose Duplicate or Create Template.

1

Duplicate Plan Items

Duplicate Plan Items

To make a new copy of an existing plan item, hover over the item, then right-click or use the 3-dot menu and select Duplicate. To duplicate multiple plan items at once, check the boxes next to items you want to copy and then open the menu. Duplicating places a new item directly under the original with (copy) in the name.

Items can be duplicated while in Portfolio, Package, Project and Grid Views. Duplicating a . . .

Task copies the item and its Assignments.
Sub-Folder copies the folder with its Tasks and Assignments.
Project copies the project folder along with its Sub-Folders, Tasks and Assignments.
Package copies the Package, as well as all the Projects with their Sub-Folders, Tasks and Assignments.

Remaining Estimate carries over to the new plan item. Logged Progress, Changes, and Files are not duplicated. 

Information about Dependencies is provided after the table below.

Attributes and properties that are duplicated for each plan item are listed here. 

Package

Project

Sub-Folder

Task

Assignment

Package

Project

Sub-Folder

Task

Assignment

Package Color

Project Color

Sub-Folder Color

 

 

Package Status

Project Status

Sub-Folder Status

Task Schedule Status

Assignment Status (active or done)

Description

Description

Description

Description

Assignment Name

Notes

Notes

Notes

Notes

 

Work Limit

Work Limit

Work Limit

Work Limit

 

Scheduling Limit

Scheduling Limit

Scheduling Limit

Scheduling Limit

 

Custom Data Fields

Custom Data Fields

Custom Data Fields

Custom Data Fields

 

Target Dates

Target Dates

Target Dates

Target Dates

 

Remaining Estimate roll-up

Remaining Estimate roll-up

Remaining Estimate roll-up

Remaining Estimate roll-up

Remaining Estimate

 

Rate Sheet

 

 

Cost Codes

 

 

 

Task type: Tracking Only or Scheduled

Assignment Scheduling: In Order or Independently

 

 

 

ASAP Scheduling

 

Dashboard filters, layout & widgets

Dashboard filters, layout & widgets

 

 

 

Member Access*

Member Access*

 

 

 

*Member Access settings for Packages and Projects are available with the ULTIMATE Plan.

Dependencies

Duplicating Tasks with dependencies:

Predecessors are carried over to the new Task.
Successors are not carried over to the new Task.

Duplicating a Package, Project or Sub-Folder with dependencies:

The container’s Predecessors are carried over to the new plan item.
The container’s Successors are not carried over to the new plan item.
Predecessor and Successor dependencies on plan items within the container are preserved.

2

Turn a Project or Package into a Template

Create Project or Package Template

To convert a Package or Project into a Template, hover over the item, then right-click or use the 3-dot menu and select Create Template. When converting a Project you’ll be prompted to select a package location within the Templates Collection.

Add Template adds the Project to the Templates Collection and closes the modal.
Close closes the modal and cancels the action.
Go to TEMPLATE Collection navigates to the Templates Collection without creating a new template.

Projects can be converted while in Portfolio View, Package View, Project View or a Project Grid. Packages can be converted from Portfolio View, Package View and Package Grid. A converted Package lands at the bottom of the Package list in the Templates Collection. Learn about managing Templates in the Templates Collection lesson.

When converting, Total Work (Logged + Remaining) from the original assignment becomes the Remaining Estimate in the Template.

Scroll down to the end of this section to see how dependencies are treated when converting Packages and Projects into Templates.

The attributes below are updated when the new Template is created. 

Package

Project

Sub-Folder

Task

Assignment

Package

Project

Sub-Folder

Task

Assignment

Package Status = Template

Project Status = Template

Sub-Folder Status = Template

Task Schedule Status = Workspace Default Status

Assignment Status = Active

Total Work roll-up converts to Remaining Estimate roll-up

Total Work roll-up converts to Remaining Estimate roll-up

Total Work roll-up converts to Remaining Estimate roll-up

Total Work roll-up converts to Remaining Estimate roll-up

Total Work converts to Remaining Estimate

Logged Progress roll-up reverts to 0

Logged Progress roll-up reverts to 0

Logged Progress roll-up reverts to 0

Logged Progress roll-up reverts to 0

Logged Progress = 0

Target Dates are CLEARED

Target Dates are CLEARED

Target Dates are CLEARED

Target Dates are CLEARED

 

 

 

 

ASAP scheduling reverts to ASAP as Prioritized

 

Member Access is CLEARED*

Member Access is CLEARED*

 

 

 

*Member Access settings for Packages and Projects are available with the ULTIMATE Plan.

This information is carried over to the new template without change:

Package

Project

Sub-Folder

Task

Assignment

Package

Project

Sub-Folder

Task

Assignment

Package Color

Project Color

Sub-Folder Color

 

 

Description

Description

Description

Description

Assignment Name

Notes

Notes

Notes

Notes

 

Work Limit

Work Limit

Work Limit

Work Limit

 

Scheduling Limit

Scheduling Limit

Scheduling Limit

Scheduling Limit

 

Custom Data Fields

Custom Data Fields

Custom Data Fields

Custom Data Fields

 

Uploaded Files

Uploaded Files

Uploaded Files

Uploaded Files

 

 

Rate Sheet

 

 

Cost Codes

 

 

 

Task type: Tracking Only or Scheduled

Assignment Scheduling: In Order or Independently

Dashboard filters, layout & widgets

Dashboard filters, layout & widgets

 

 

 

Dependencies

Creating a Project Template:

The Project’s Predecessor and Successor dependencies are not carried over to the Templates Collection.
Predecessor and Successor dependencies on plan items within the Project are preserved.

Creating a Package Template:

The Package’s Predecessor and Successor dependencies are not carried over to the Templates Collection.
Predecessor and Successor dependencies on plan items within the Package are preserved.