The Issue Timesheet is useful for searching for worklogs for a particular JIRA Issue.
The issue timesheet for a JIRA issue with sub-tasks (click to enlarge)
Accessing the issue timesheet
Required permission
- Browse Project permission for the issue's project
- View All Worklogs permission for the project (if you want to so that you can view worklogs of other users on the timesheet)
Procedure
- On the main menu bar, click Tempo > Timesheets.
- On your user timesheet, in the upper-left corner, click User > Issue.
Reading the initial information columns
Symbol | P | B | Σ |
---|---|---|---|
Stands for | Planned hours | Billed hours | Logged hours |
Explanation | The total number of planned hours in the row, in the displayed time period. | The total number of billed hours in the row, in the displayed time period. | The total number of logged hours in the row, in the displayed time period. |
Note | The 'Billed hours' column is displayed if one or both of the following conditions are met:
Related topic |
Reading the 'total' rows
Daily hours total | Refers to logged hours |
---|---|
Weekly hours total | Refers to logged hours |
Planned hours total | Refers to daily planned hours |
Total | Today | Period |
---|---|---|
Worked | All logged hours for the displayed period that are before or on today's date | All logged hours for the displayed period |
Planned | All planned hours for the displayed period that are before or on today's date | All planned hours for the displayed period |
Required | The team's required working hours for the displayed period that are before or on today's date | The team's required working hours for the displayed period |
Displaying worklogs from sub-tasks
By default, the timesheet displays one row for each issue. If an issue has sub-tasks, you can display the sub-tasks by selecting the 'Include sub-tasks' check box in the upper-left corner of the timesheet.
The issue timesheet including sub-tasks
Switching among issues
Required permission
- Browse Project permission for the issue's project
- View All Worklogs permission for the project (if you want to view worklogs on the timesheet)
Procedure
To display the timesheet of a different issue, complete the following steps:
- On the issue timesheet, on the second menu bar from the top, click the big text; that is, the name of the displayed issue.
- From the list of issues, select or search for the issue that you want to display.
Panel | ||||||
---|---|---|---|---|---|---|
| ||||||
|