QuestionI can't seem to find a place in the new Jira issue view to edit the Remaining Estimate.
Answer

Currently remaining estimate can be edited in the new Jira issue view if the Time tracking is provided by the Jira native one, however, if Tempo is set to be the Time tracking provider, the only way to edit the remaining estimate of an issue is to either log time on it or edit an existing worklog. In the Log Time or Edit Worklog pop-up window, you will be able to enter a new value for the Remaining estimate field.

If this is not possible, you would have to change it back to the old issue view and edit the Remaining Estimate through editing the issue, given that the "Time Tracking" Field is added to the "Edit Issue" screen.