This article is for Cloud. Visit Data Center

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Current »

The Time Balance report for Jira Cloud displays all changes in the time tracking fields for issues in a certain period.

Note: There is no access to worklogs from this report page.

time_balance_callouts.png

Element

Description

Details

A

Previous and Next icons

Select to scroll to the previous or next week.

B

Time display dropdown

Select to display the day, week, or month.

C

Worked Hours dropdown

Select to display the daily, weekly, or monthly worked hours.

D

Details button

Enable to display every worklog. When disabled, entries are grouped by issue.

E

Time Spent column

Displays the sum of worklogs for an issue, during the period selected. Note: There is also a Jira issue Timespent field, which is the overall value of time logged for an issue.

F

Estimate column

Displays Time Spent + Est. Time Remaining.

G

Variance column

Displays the time variance, calculated as Original Estimate - Estimate (Time Spent + Est. Time Remaining).

H

Original Estimate column

Displays the initial estimated time specified in the issue field.

I

Progress Column

Displays a progress bar to visualize the progress per issue. Calculated as Time Spent / ( Est. Time Remaining + Time Spent). Displays as 100% when Est. Time Remaining is 0.

J

Total row

Displays the total time per time column and the total progress for the displayed table.

  • No labels