Jira-based Baselines
Jira-based baselines allow you to compare the current task timelines to timelines found in a Jira custom field. This allows you to compare the current chart to a previously planned schedule, alternate schedule, transition dates, or any other date/time data available in Jira.
Creating a Jira-based Baseline
To create a new baseline, open the Baseline menu in the Gantt toolbar and select Create New.
Give the baseline a name and select Jira-based baseline from the Type dropdown.
Enter the following information:
Start Date - Select the custom field that contains the start dates that should be used to schedule tasks for the baseline.
Finish Date - Select the custom field that contains the finish date that should be used to schedule tasks for the baseline.
- Treat task with only Start Date value as a milestone - If this option is selected, tasks that only have a value in the Start Date field will appear as milestones in the baseline.
- Treat task with only Finish Date value as a milestone -Â If this option is selected, tasks that only have a value in the Finish Date field will appear as milestones in the baseline.
In order to create a baseline, you must be the structure owner or have Edit permissions for the structure.
Viewing a Baseline
Once created:
If there are start and finish values available for a task, it's baseline will appear as a dotted line in the same row as the current task
If you selected either of the One date-field tasks options, any issue with only a start/finish date will have a milestone baselineÂ
- If there are no dates for a task, or only one date that does not match the One date-field tasks selection, no baseline will appear for that task