This article is for Cloud. Visit Data Center
List of Gantt Fields Available in Structure
The following Gantt fields can be used within Structure columns. To learn more, see Gantt Fields in Structure.
Name | Result |
---|---|
Gantt Appearance | The color of the item in the Gantt chart. Most issues will return "blue" unless they are affected by a configuration slice with a custom color scheme. |
Gantt Critical Path | Returns "Critical" if the item is part of the critical path. |
Gantt Duration | The duration of the task within the Gantt chart. |
Gantt Finish Date | The task's finish date. |
Gantt Fixed Duration | The task's fixed duration, if the task has a fixed duration. |
Gantt Manual Finish Date | If a task has a manual finish date, returns that date value. |
Gantt Manual Milestone Date | If a task has a manual milestone date, returns that date value. |
Gantt Manual Start Date | If a task has a manual start date, returns that date value. |
Gantt Max Units | The maximum number of resource units that can be allocated for the task at any given time (see Configuration | Resources). |
Gantt Milestone Date | If an item is visualized as a milestones within the chart, returns the milestone date. |
Gantt Progress | The calculated progress for the task. |
Gantt Resource | The resource assigned to the task. |
Gantt Scheduling Error | If a scheduling conflict exists, returns "Error" |
Gantt Scheduling Mode | Returns "Auto" if the task is automatically scheduled, "Manual" if the task is manually scheduled, "Agile" if scheduled by sprint. |
Gantt Slice | If the task's behavior or appearance is effected by a configuration slice, returns the corresponding slice's name. |
Gantt Start Date | The task's start date. |
Gantt Type | How the task is displayed in the Gantt chart: task, group or milestone. |
Gantt Work | The task's work estimate (returned as a time value), based on the Gantt configuration. If Work has been manually entered in the Task Details Panel, returns this value. |